Sprints, Goals and Key Results

Plan work in time boxed sprints with a live burndown and velocity, and measure each project against an objective with key results: cards done, a number you update, or a live Brain goal.

Updated

What it does

Sprints are time boxes (two weeks by default) with the cards your team commits to. The Sprints view in a project shows:

  • the sprint's dates, goal and status (Planned, Active, Closed),
  • committed, done and still open work, and days left,
  • a burndown: remaining hours (or remaining cards when nothing is estimated) at the end of each day, against the ideal straight line. Hover a day to see both numbers,
  • velocity: how much the team finished per sprint over the last three closed sprints, so you know how much to take on next time,
  • the backlog: open cards that are not in a sprint.

A card is in at most one open sprint at a time. Closing a sprint moves unfinished cards to the next sprint or back to the backlog.

Goals and key results make the project an objective. Key results measure it three ways and roll up into one progress number on the Dashboard:

  • Cards done: the share of cards with a label that are done.
  • A number: something you update, for example "First 25 reviews".
  • A Brain goal: a live goal from Brain rules, Goals (for example days of cover), measured hourly by your Brain.

The target date you set here is what the Risk radar checks the predicted finish against.

When to use it

  • Teams that work in weekly or two weekly cycles (listing fix sprints, content sprints).
  • Launches and seasonal projects with clear outcomes you want to measure.

Step by step

  1. Open the project and click Sprints in the views.
  2. Click New sprint, set the dates and goal, and Save.
  3. Add cards from the backlog (Add to a sprint) or with Add cards.
  4. Click Start sprint. The committed hours are locked in for the burndown.
  5. At the end click Close sprint and choose where unfinished cards go.
  6. For goals open the Dashboard and click Set the Goal (or Edit Goal) on the Goal card: add an objective, a target date and key results, then Save Goal. The Goal card is the one place for them; the Risk radar measures against its target date.

Every button and setting

  • Edit: rename or change dates and goal.
  • Remove from sprint (x): sends a card back to the backlog.
  • Sprint on a card: move a card between sprints from the card itself.

FAQ

Hours or cards? The burndown uses hours when cards have estimates, otherwise cards.

Can two sprints run at once? No. Close the running one first.

Troubleshooting

  • Burndown is flat: cards are done but have no completion today, or cards have no estimates; add estimates.
  • "Pick one of your Brain goals": the goal was deleted or belongs elsewhere. Pick it again in the list.