Build finished products from their components. Keep a versioned bill of materials per product (with sub-assemblies, scrap, labour and overhead), see how many you can build, and run production orders that reserve parts, record what was built and cost it from FIFO.

Updated

What it does

Manufacturing is for products you make yourself: candles from wax and wicks, gift sets from boxes and cards, a lamp from a base, a shade and a bulb.

  • Bill of materials (BOM). Each finished product has a list of components: how many of each go into one unit, the unit of measure and a planned scrap percentage. Add a labour and an overhead cost per unit if you track them. A component that has its own BOM is a sub-assembly, so a BOM can be several levels deep. A BOM that would loop back to itself is refused.
  • Versions. Change a BOM by starting a new version. One version is active at a time; production orders keep the version they were built from.
  • Can Build. For every product with a BOM you see how many units your stock can build today, including sub-assemblies you would build first from their own parts. A part two sub-assemblies both use is never counted twice.
  • Production orders. Draft, then Release: the components are reserved, so no channel or order can sell them. Record what was built (all at once or in parts), what was scrapped, and the lot code or serial numbers when the product tracks them. Components leave stock and the finished units arrive through the stock ledger, once, even if you press the button twice.
  • True cost. The finished unit cost is the FIFO cost of the components used, plus labour and overhead. Scrapped units carry no stock; their cost lands on the good units.

When to use it

  • You make, assemble or kit products before you sell them (not at the moment of sale: that is a bundle).
  • Your Brain proposes Build 120 x Gift Box: all components in stock or Build 80, short 2 components: buy them in Daily Tasks.
  • You want to know how many you can make before you promise a wholesale order.

Step by step

  1. Open Inventory, Manufacturing.
  2. Products that already have assembly components show Import As BOM. Press Import All to keep them as version 1. Nothing is lost and the old Build button keeps working.
  3. Press New Bill of Materials, pick the finished product and add components with Qty Per Unit, Unit and Scrap %. Add Labour Cost Per Unit, Overhead Cost Per Unit and Build Days if you use them. Press Save and Make Active.
  4. The Cost Roll-Up shows each component, sub-assemblies opened up, and the cost of one unit from your real FIFO costs.
  5. Press Build on a product (or New Production Order), enter the quantity and the warehouse, and press Check Components to see shortages and lead times. Press Create and Release.
  6. If parts are short: Create Sub-Assembly Orders makes production orders for short sub-assemblies, and Draft Purchase Orders drafts one PO per supplier for the bought parts. You review and send them.
  7. When units are made, open the order and press Record Production. Enter Built and Scrapped, plus the lot code or serials if asked. Record more later until the order is done.
  8. A finished order shows Completed. Press Close when the paperwork is done, or Close Short to stop an order early. Cancel releases every reserved part while nothing has been recorded yet.

FAQ

What is the difference with a bundle? A bundle has no stock of its own: selling one takes its parts at the moment of sale. A manufactured product is built ahead of time and sold from its own stock.

Does the Brain buy the finished product? No. Products with an active BOM are built, not bought, so the Restock planner leaves them to the production task. Parts a released order is short of are counted as demand once, so the restock task proposes buying them.

Can Autopilot create production orders? No. Building commits components, so it always waits for you. You can change the quantity before you approve; the server caps it at ten times the proposal.

Where do reserved parts show? In the product's Reserved number and as Reserve rows in the Stock ledger.

Who sees costs? Roles without cost access (warehouse staff) see quantities only.

Troubleshooting

  • Release says some parts are short: the order reserved what was free. Receive the parts, then press Reserve Again, or buy them with Draft Purchase Orders.
  • Record Production says not enough components: an order or another build used them. Check the components and try again; nothing moved.
  • A BOM cannot be saved: a component may be the product itself, a bundle, or lead back to it through a sub-assembly.